Pre-Construction
Sep 21, 2012 - Submitted NVR Loan Application
Sep 21, 2012 - Guardian Cable & Wiring Meeting
Sep 25, 2012 - CTI Flooring Selections Meeting
Oct 16, 2012 - Loan Application Sent to NVR Underwriting
Dec 06, 2012 - NVR Denied Loan Approval (There will definitely be a post about this experience)
Dec 06, 2012 - Loan Application Submitted to Outside Bank (non-NVR)
Dec 09, 2012 - Structural and Non-Structural Options Locked In
Dec 10, 2012 - Loan Approval from Outside Bank
Dec 14, 2012 - Pre-Construction Meeting (Lot Stake Out)
Construction
Dec 18, 2012 - Basement Walls Poured
Dec 26, 2012 - Loan Rate Locked In
Jan 05, 2013 - Basement & First Floor Framed
Jan 09, 2013 - House Framing Complete
Jan 12, 2013 - Shingles Laid Roof Complete
Jan 12, 2013 - Plumbing Started
Jan 18, 2013 - Sprinkler and Electrical Systems Started
Jan 18, 2013 - Guardian Cable & Wiring In Home Appointment
Jan 23, 2013 - Home Frame Independent Inspection
Jan 23, 2013 - Pre-Drywall Walkthrough
Jan 24, 2013 - Insulation Installed
Jan 25, 2013 - Energy Star & Insulation Inspection
Jan 25, 2013 - Drywall Delivered
Jan 29, 2013 - Sprinkler System Inspection by State Fire Marshall
Jan 29, 2013 - Drywall Started
Feb 01, 2013 - Vinyl Siding Complete
Feb 02, 2013 - Drywall Complete
Feb 04, 2013 - First Coat of Paint
Feb 06, 2013 - House Trimmed Inside & Out
Feb 06, 2013 - Vinyl Floors Laid, Cabinets Installed, Counter Tops Installed, Stair Balusters Installed
Feb 06, 2013 - Outside Stone Complete
Feb 08, 2013 - Electricity On & 2nd Coat of Paint
Feb 13, 2013 - Driveway Fully Paved, Appliances Installed, Some Light Fixtures Installed, Commodes, Faucets & Shelving Installed
Feb 13, 2013 - Guardian Options Installed
Feb 20, 2013 - Sod Laid/Landscaping
Feb 21- Mar 5 - Inspections, 3rd Coat of Paint, Paint Touch Ups, Home Cleaned Several Times, Drywall Touch Ups, Other Touch Ups/Fixes, Etc.
Mar 06, 2013 - Pre-Settlement Walk Thru
Mar 13, 2013 - Settlement
Mar 15, 2013 - Moving Day